Heat networks: what landlords need to do before 26 January 2027

Mia Rotaru 17 November 2026

If you let flats in a building with communal heating, there’s a new regulatory deadline you should be aware of. Ofgem became the regulator for heat networks across Great Britain in 2026, bringing the sector in line with gas and electricity regulations. Most importantly for landlords, existing heat networks must be registered with Ofgem by 26 January 2027.

And with hefty fines of up to 10% of an organisation’s turnover or £1m (whichever is higher), as well as potential redress payments to customers it is essential you ensure you are complaint. 

What exactly is a heat network - and do the new rules affect me?

A heat network supplies heating, hot water or cooling from a central source to multiple customers. There are two main types: 

  • Communal heat networks serve one building with multiple units, such as a block of flats. 
  • District heat networks serve two or more buildings. 

Most residential blocks with communal heating fit these definitions. Flats with their own gas boilers or individual heat pumps do not. 

Most houses in multiple occupation (HMOs) are exempt. The exception is section 257 HMOs, which include buildings converted into self-contained flats that do not meet the relevant 1991 or subsequent building regulations, or in which fewer than two-thirds of the flats are owner-occupied.

These properties remain within scope of the upcoming regulations.

Am I the operator?

In a leasehold building with communal heating, the freeholder is usually treated as the heat network operator, because they typically control the building and the heating system. That can change if the building is run another way, in which case a Right to Manage (RTM) company or a Residents’ Management Company (RMC) may be the operator instead. 

Ofgem-focused guidance advises each party to assess its own position against the definitions, rather than assuming an answer from whoever holds the freehold.  

You may also be a 'supplier', that is the person who owes the customer the supply obligation under a lease or supply agreement. Operator and supplier are separate roles, and you may be one or both.

What does “deemed authorisation” mean?

From 27th January 2026, operating or supplying a heat network without authorisation will be an offence. 

Anyone already operating or supplying on a heat network is automatically treated as authorised and does not need to apply again (this is called a deemed authorisation), but they are still required to register by 26 January 2027.

Registration requires information about the network’s technical characteristics, how it operates and who its customers are and is one part of the compliance process. The authorisation conditions also cover how you bill customers, handle complaints, support vulnerable customers and manage disconnection, and these apply whether or not you have registered.

What if I miss the deadline?

If you don’t register in time, you lose your deemed authorisation, and continuing to operate or supply without authorisation may result in fines and enforcement action from Ofgem.

Ofgem has the power to impose financial penalties of up to 10% of an organisation’s turnover or £1m (whichever is higher), and redress payments if harm has been caused to customers. However, Ofgem has said it wants the heat networks industry and consumer bodies to fully understand the challenges and will bring in a proportionate and effective approach. 

Remember - any new network or any regulated activity that starts after the deadline requires a full authorisation application before it begins.

What do I need to do?

In terms of your first steps: 

  1. Check whether your building has a heat network and, if so, whether it’s communal or district.

  2. Work out who the operator and supplier are. Check your lease, any management agreement and whether an RTM or RMC is involved. If it’s unclear, take advice. 

  3. Register early. Registration is already open, and leaving it late gives you no time to resolve problems such as split registrations or several operators. Check what you need to do to prepare for registration, then can register using this page.

You can find more information about Ofgem’s guidance here. 